SMACNA FibrousGlassDuctConstructionStandards 2003 07E
$86.13
Fibrous Glass Duct Construction Standards, 7th Edition
Published By | Publication Date | Number of Pages |
SMACNA | 2003 | 88 |
Provides the performance characteristics for fibrous glass board as determined by the North American Insulation Manufacturers’ Association (NAIMA) and Underwriters Laboratories (UL) as well as specifications for closures and illustrations of how to construct the full range of fittings. Also covers details for connections to equipment and air terminals, hanger schedules, reinforcement requirements, fabrication of rectangular duct and fittings, closures of seams and joints, channel and tie rod reinforcements, plus hangers and supports. For 2” wg or less. Metric units have been provided in a more convenient format, as well as an updated inspection checklist.
PDF Catalog
PDF Pages | PDF Title |
---|---|
5 | FOREWORD |
6 | REFERENCES |
7 | NOTICE TO USERS OF THIS PUBLICATION |
11 | TABLE OF CONTENTS |
12 | TABLES |
13 | FIGURES |
17 | INTRODUCTION CHAPTER 1 INTRODUCTION 1.1 MODEL PROJECT SPECIFICATION |
21 | CHAPTER 2 DUCT PERFORMANCE CHARACTERISTICS 2.1 FIBROUS GLASS DUCT PERFORMANCE CHARACTERISTICS |
22 | 2.2 USE IN MEDICAL FACILITIES 2.3 OTHER PERFORMANCE CHARACTERISTICS |
25 | CHAPTER 3 SPECIFICATIONS AND CLOSURE 3.1 GENERAL SPECIFICATION REQUIREMENTS |
26 | 3.2 CLOSURES |
28 | FIGURE 3-1 CLOSURES |
29 | FIGURE 3-2 CLOSURES (CONTINUED) |
33 | CHAPTER 4 FITTINGS AND CONNECTIONS FIGURE 4-1 ONE-WAY TRANSITIONS |
34 | FIGURE 4-2 TWO-WAY TRANSITIONS |
35 | FIGURE 4-3 ELBOWS |
36 | FIGURE 4-4 OFFSET |
37 | FIGURE 4-5 TEES AND BRANCH TAKE OFFS |
38 | FIGURE 4-6 90 DEGREE ELBOWS WITH TURNING VANES |
39 | FIGURE 4-7 ENTRY BRANCH AND SPLITTER DAMPER |
40 | FIGURE 4-8 END CAPS |
41 | FIGURE 4-9 FLANGE ON OPENING |
42 | FIGURE 4-10 SHEET METAL AND EQUIPMENT CONNECTION DETAILS |
43 | FIGURE 4-11 SHEET METAL AND EQUIPMENT CONNECTION DETAILS (CONTINUED) |
44 | FIGURE 4-12 REGISTER AND GRILLE ATTACHMENT |
45 | FIGURE 4-13 DIFFUSER CONNECTION |
49 | CHAPTER 5 REINFORCEMENT FIGURE 5-1 TIE ROD TERMINATION METHODS |
50 | FIGURE 5-2 TIE ROD REINFORCEMENT Table 5-1 Tie Rod System Reinforcement Schedule |
51 | FIGURE 5-2M TIE ROD REINFORCEMENT Table 5-1M Tie Rod System Reinforcement Schedule |
52 | FIGURE 5-3 TIE ROD REINFORCEMENT AT JOINT |
53 | FIGURE 5-4 CHANNEL REINFORCEMENT EXAMPLES— POSITIVE PRESSURE |
54 | Table 5-2 Channel System Reinforcement Schedule |
55 | Table 5-2M Channel System Reinforcement Schedule |
56 | FIGURE 5-5 PARTIAL WRAP-AROUND REINFORCEMENT Table 5-3 Partial Wrap-Around Reinforcement Schedule |
57 | FIGURE 5-6 PARTIAL WRAP-AROUND REINFORCEMENT Table 5-3M Partial Wrap-Around Reinforcement Schedule |
58 | FIGURE 5-7 CHANNEL REINFORCEMENT— NEGATIVE PRESSURE SYSTEMS |
59 | FIGURE 5-8 FITTING REINFORCEMENT—90 DEGREE ELBOWS |
60 | FIGURE 5–9 REINFORCEMENT—90 DEGREE ELBOWS |
61 | FIGURE 5-10 REINFORCEMENT—BRANCH CONNECTIONS |
62 | FIGURE 5-11 REINFORCEMENT—TEES |
63 | FIGURE 5-12 REINFORCEMENT—OFFSETS AND MITERED ELBOWS |
64 | FIGURE 5-13 REINFORCEMENTS—TRANSITIONS |
65 | FIGURE 5-14 REINFORCEMENT—ACCESS DOORS |
66 | FIGURE 5-15 REINFORCEMENT—END CAPS |
69 | CHAPTER 6 HANGERS AND SUPPORTS FIGURE 6-1 ALLOWABLE HANGER SPACING, STRAIGHT DUCT, 3 IN. (75 MM) WIDE CHANNEL |
70 | Table 6-1 Maximum Hanger Spacing By Duct Size ID Table 6-2 Channel Selection |
71 | FIGURE 6-2 HANGING DUCT |
72 | FIGURE 6-3 HANGING DUCT FITTINGS UP TO 48 IN. (1.22 M) WIDTH |
73 | FIGURE 6-4 HANGING DUCT FITTINGS UP TO 48 IN. (1.22 MM) WIDTH (CONTINUED) |
74 | FIGURE 6-5 VERTICAL RISER SUPPORT |
75 | FIGURE 6-6 ELECTRIC HEATER SUPPORT |
76 | FIGURE 6-7 VOLUME DAMPER INSTALLATION |
79 | APPENDIX CONTRIBUTORS TO FORMER EDITIONS OF THE SMACNA FIBROUS GLASS DUCT CONSTRUCTION STANDARDS Committees for First and Second Editions Committees for Third Edition Committees for Fourth Edition |
80 | Committees for Fifth Edition Committees for Sixth Edition |
81 | Inspection Checklist for Fibrous Glass Duct System Installation |
83 | INDEX |